• thumb2
  • thumb2

Welcome to Mifflin County School District

  • 2013-2014 Calendar

     

    The Indian Valley Elementary School has been under construction for forty-three (43) weeks, since the Notice to Proceed, was issued on February 26, 2013.  The baseline schedule completion date is February 28, 2014.

    Phase 3:

    The work at the Indian Valley Elementary School continues with the 3rd and final phase of the project.

     Phase 3 consists of the music and art rooms and is currently in the finish stages.  Drywall finishing is complete and painting is starting; to be followed by ceiling, casework, and flooring.  Work is also continuing with the elevator, which we expect delivery the week of January 20, 2014. 

     The concrete work for the exterior steps out of the cafeteria is complete and framing for the canopy roof is scheduled to start the week of January 20, 2014.

     Most items are on the schedule for completion by our contract date of February 28, 2014; however, there are some items that will be complete in the early Spring that are weather dependent.

Scroll To Top