IVES Project Update from Reynolds’s Construction

The Indian Valley Elementary School has been under construction for forty-three (43) weeks, since the Notice to Proceed, was issued on February 26, 2013.  The baseline schedule completion date is February 28, 2014.

Phase 3:

The work at the Indian Valley Elementary School continues with the 3rd and final phase of the project.

 Phase 3 consists of the music and art rooms and is currently in the finish stages.  Drywall finishing is complete and painting is starting; to be followed by ceiling, casework, and flooring.  Work is also continuing with the elevator, which we expect delivery the week of January 20, 2014. 

 The concrete work for the exterior steps out of the cafeteria is complete and framing for the canopy roof is scheduled to start the week of January 20, 2014.

 Most items are on the schedule for completion by our contract date of February 28, 2014; however, there are some items that will be complete in the early Spring that are weather dependent.


IV Updated Renovation Pictures

IVEC Construction  

click here to see other pictures now.


IV Policy and Compact

2013-2014 Parent and Family Involvement Policy

Title I Home-School Compact


Air Quality Control

Response to the concerns expressed by members of the public about the Indian Valley Elementary and Intermediate School air quality.

JM I Environmental Corp regarding indoor air quality samples
JMSI Environmental Corp Indoor Air Quality Study Report for September 3, 2013

Forms and Flyers

Parent Teacher Conference Brochure

Parent/Guardian Right to Know Information 2013-2014

2013-2014 Indian Valley Welcome Letter

Drop-off and Pick-up Procedures

Safe Home Directory