[MCSD] - [Schools] - [IVHS] - [IVHS-10]

[Web Mail]  -  [Intranet]  

  

[[ Documents]   [Groundbreaking]  [Schematic]   [Timeline ] [Construction Site Images ]


Mifflin County School District

Indian Valley High School
Building Project

Project Timeline

IVHS Project Timeline
updated July 31, 2009

 
bullet

The Mifflin County School Board gave the initial approval to begin planning the new high school on November 17, 2005.
 

bullet

The new high school will be built on property owned by the School District above the current high school and above the new track and athletic field.
 

bullet

On December 7, 2005, plans were formed to purchase some additional property northwest of the site and northeast of the site.
 

bullet

On December 21, 2005, a project team kick-off meeting was held involving members of the Administration team, representatives from Hayes Large Architects, and Reynolds Construction.
 

bullet

On January 5, 2006, a meeting was held with a team of faculty members from the current IVHS staff to lay plans for educational specifications and prepare room schedules.
 

bullet

Visitations to other new high schools in the state began on January 9, 2006 and other visitations followed.
 

bullet

The School Board reviewed room schedules, educational specifications, and topographic surveys on February 23, 2006.
 

bullet

On July 5, 2006, a second Preliminary Meeting was held with Mifflin County Planning Staff and Derry Township.
 

bullet

September 11, 2006, Geotechnical Investigations began.
 

bullet

Act 34 Public Hearing was held on January 11, 2007.
 

bullet

Bids for construction were reviewed on September 6, 2007.
 

bullet

The building will be constructed to house 1150 students, grades 9-12, with an approximate cost of $62-64 million dollars.
 

bullet

The bids for the project were awarded on July 24, 2008
 

bullet

The Department of Education has approved the project to proceed.
 

bullet

Plans call for construction to begin soon after August 18, 2008.
 

bullet

Long-range plans call for IVMS to move to the current IVHS when the new high school is completed. This move supports the campus approach which the school district believes improves security, provides more flexibility for student enrollment shifts up or down, and provides for sharing staff and other resources.

February 19, 2009 update

bullet

The projected final completion in all areas is anticipated to be December 22, 2010.
 

bullet

Building pads are being graded and rolled in preparation for foundation work.
 

bullet

Geothermal wells are being drilled.
 

bullet

Masonry foundation walls are being built.
 

bullet

Below-grade electric and plumbing is being installed.
 

bullet

 More permanent fencing is being installed around the site.
 

bullet

Sanitary pipes are being installed.
 

bullet

Preparation is being made for steel installation.

July 31, 2009 update

 The new Indian Valley High School has been under construction for approximately forty three (43) weeks sine the Notice to Proceed was issued on August 25, 2008. the projected substantial completion is anticipated as December 22, 2010.

bullet

Phase 1 - Area B

 All slab on deck placement is complete and the slab on grade is scheduled     for the 2nd week of July.  The high roof areas are decked in and we anticipate roofing to start in the next month. Fireproofing of steal is scheduled with Mechanical, Plumbing and Electrical rough-ins to follow. the exterior masonry wall will also follow fireproofing.

bullet

Phase 2 - Area A

 The structural steel erection is complete including decking floors. The roof deck is currently being installed and slab on deck pours are scheduled for the 3rd week of July. Underground plumbing is continuing with anticipation for placing slab on grade the last week of July.     

bullet

Phase 3 - Area E

 The remainder of the pad was excavated. the layout, excavation and placing of footings will be complete the 2nd week of July followed by the foundation walls.

bullet

Phase 4 - Area D

 The excavation and placement of footings have started in the auditorium and kitchen areas which will be followed by foundations and masonry bearing walls.

bullet

Phase 5 - Area C

 The remaining of the building pad is being excavated which will be followed by the installation of the footings.

bullet

Side Work

  Grading has started for the installation of the reinforced soil slopes at the track. Cedar Street is being prepared to receive paving by the end of July.

 The Geothermal Well drilling is complete and the horizontal underground piping is proceeding.

 The soil nail is complete with the exception of the final finish coat. This is scheduled to start prior to the end of the month.


Back to previous page Back to previous page

Revised: Thursday, August 27, 2009

URL: http://www.mcsdk12.org/ivhs09


Select this image to return to the Mifflin County School District home page.Copyright © 2006-09 MCSD. All rights reserved.
Comments to MCSD may be directed to: MCSD
Comments to the webmaster may be directed to: webmaster
Mifflin County School District, 201 Eighth Street - Highland Park, Lewistown, PA 17044
MCSD Disclaimer